The Soaring Eagle Water Park & Hotel design includes a 244 hotel room, a 45,000 square foot indoor water park that features a waver rider, one body slide, one bowl slide, a rock climbing wall, lazy river, children's play area and a private adult pool.  It will also include a full service restaurant that seats 134 indoor and 72 outdoor patrons, an arcade and other traditional hotel amenities.  The newly built facility will also incorporate a pro shop which will run the existing golf course.

Horizon Construction Group based out of Madison, Wisconsin has been hired as the General Contractor for this project.  Progress reports and pictures will be updated on a monthly basis.


PROGRESS REPORT (As of January 9, 2012):

Site Work: 98% Complete. Courtyard is near completion; grass pavers on the north side of job will be completed in Spring.
Site Utilities:  98% Complete.  Miscellaneous utility tie-ins are ongoing.
Concrete: 98% Complete. Site concrete is almost complete; One slab pour remaining in the waterpark and will be completed by end of month.
Masonry:  75% Complete.  Entrance stone is complete; Interior stone work is ongoing.  Court yard piers to be complete this month.
Structural Steel:  85% Complete.  Misc steel is ongoing
Rough Carpentry: 95% Complete.  Building A - Exterior bracket install is ongoing; Tower B & C Stair treads to be completed this month.
Glulam Construction:  100% Complete.
Windows:  100%  Complete.
Foundation Insul/Waterproofing:   100% complete
Roofing:
  98% Complete.  Building A - Sheet metal install is scheduled for completion this month; Tower B & C - Complete.
EIFS: 98% Complete.  Building A - Misc. EIFS work & touchups remaing.
Doors/Hardware:  65% Complete.  Tower B doors are set & hardware installed;  Tower C doors are ongoing.  Building A - Doors are onsite and install will start this month.
Drywall:  85% Complete.  Tower B & C- drywall is complete;  Building A - Drywall is installed and wall finish is ongoing throughout the lobby area.
Flooring:  40% Complete.  Tower B - 1st floor and corridor carpet is ongoing.  Tower C - 3rd floor carpet work to start next week; Building A - Tile work in kitchen & employee restroom is complete.
Painting:  65% Complete.  Tower B - Unit paint & VWC is complete, Corridor VWC will be complete this week; Tower C - Finishing up on 1st floor unit VWC; Building A - Waterpark painting work ongoing, back of house work is ongoing.
Fire Protection:  85% Complete.  Building A - Misc. rough-in work is ongoing.  Tower C - Trim work is ongoing.
Plumbing:  85% complete.  Building A - Back of house rough in work is ongoing;  Tower B - Water hookups are complete; Tower C - finish work is ongoing on 1st floor.
HVAC:  80% Complete.  Tower C - Heat pump startup is ongoing;  Building A - Ceiling work is ongoing in restraint & lobby.  Controls programming has started.
Electrical:  75% Complete.  Building A - Rough in work is nearly complete;  Tower B - Corridor light install is ongoing; Tower C - Finish/trim work is ongoing on 2nd floor.
Aquatics:  85% Complete.  Flow Rider install is ongoing; Aquatic Play Structure install is complete.  Pool finishes are scheduled to be complete in February.
Slides:  99% Complete.  Slides are complete.  Proslide will be back for slide start up.

PROGRESS PICTURES:

CLICK TO EXPAND OR CLOSE: PROGRESS PICTURES UP TO JUNE 2011

CLICK TO EXPAND OR CLOSE: PROGRESS PICTURES FOR JULY 2011
CLICK TO EXPAND OR CLOSE: PROGRESS PICTURES FOR AUGUST 2011
CLICK TO EXPAND OR CLOSE: PROGRESS PICTURES FOR SEPTEMBER 2011
CLICK TO EXPAND OR CLOSE: PROGRESS PICTURES FOR OCTOBER 2011

CLICK TO EXPAND OR CLOSE: PROGRESS PICTURES FOR NOVEMBER 2011

 




Copyright 2009 Migizi Economic Development Develop, Operate And Manage Economic Enterprises On Behalf Of The Tribe
Website Designed & Powered By: DIGITAL DESIGNS: Michigan #1 Web Design Company